Friday, July 10, 2009

Tyranena Substation Activity

1. The majority of the foundations have been installed. The remaining foundations will be completed in the coming weeks.
2. Conduit and grounding should be installed in the next two weeks,
3. The first of the two transformers was delivered on June 30th. The other transformer is expected to be delivered in late July or early August.
4. The majority of the equipment needed for the substation has been delivered and will be installed in the next two months.
5. The crushed stone surface for the substation will be placed during the week of July 27th.
6. Fence work is anticipated to begin the week of August 3rd.
7. The substation control building is scheduled to arrive in late August.