The City has asked that WisDOT initiate and effect
the State Highway “89” improvement from Madison Street south to Topel Street. State
Highway “89” is a connecting highway with significant deterioration of the
existing asphalt overlay which is over concrete in portions of the roadway. The
work will consist of reconstructing the existing roadway and extending the
urban curb and gutter section where none currently exists.
The State has extended a contract to the City to
complete the work with the conditions specified in the agreement included in
the packet.
BACKGROUND
The State manages major reconstruction project for
the Street and the City is responsible for regular maintenance. Major
reconstruction should occur about once every twenty to thirty years depending
on street condition. The last major reconstruction of S. Main Street by the
State occurred in the 1950s. A portion from Veterans Lane to Madison Street was
rebuilt by the State in 1962. The City’s last major project was in 1992-93 with
lane overlays from Sandy Beach Road to Veterans Lane. The City also completed a
project from Veterans Lane to Madison Street in 1998. N. Main Street was
reconstructed in 1999 by the State.
Duane Vandemausse with the City’s consulting
engineers had communicated with Mike Rewey of WisDOT in 2001 regarding a
potential reconstruction of S. Main Street because of interest in a sidewalk
project on the street. Staff was informed that the project could be in 2010.
The date kept moving back until we were informed that the project was no longer
on the list. In that time period there were a substantial number of retirements
and position changes. In 2012, City staff requested a meeting with the current
staff to discuss the project.
City staff met with Michelle Ellias and Karen Olson
from WisDOT to discuss a potential State Highway “89” project (S. Main Street).
The conversation went very well and was very informative. The needs and
estimate summary prepared by WisDOT noted that the existing roadway is a connecting
highway with cracked and rutted pavement. It has been milled and overlaid on
past projects but needs a higher level improvement with the last rebuild
occurring prior to 1950. Roadway width varies from 40 feet face to face of
curb, to variable widths of around 34 feet where there are rural cross sections
on the south side of the project. There is parking on both sides of S. Main
Street for the full length of the project.
The proposed Improvement and nature of work
include replacing pavement, curb and gutter, and storm sewer. There
will be an evaluation of intersections for signals or roundabouts, and lane
designations. The project will add pedestrian and bicycle accommodations per
Trans 75 (Complete Streets) requirements, where feasible.
The expected construction start date is the spring of 2020. If funding becomes available this project could
be constructed sooner, but several years would still be needed for design,
permitting, and right-of-way acquisition (if needed).
There are features of the project work that would be
non-participating work which will be undertaken independently by the
municipality. These include construction of pavement
utilized for parking, utility improvements and overruns of capped aesthetic
funding (if the city decides to use CSS funds).
The utility improvements (sanitary sewer and water main) could be constructed
concurrently with the DOT project in order to eliminate the need for temporary
roadway restoration. The utilities are
currently old and undersized and need to be replaced to accommodate the
ultimate service needs of the City.
ISSUE
This
agreement is the preliminary document that gets a six year process started.
Within that time period the design and economic conditions will change and this
agreement will have to flex with those changes. The estimated City’s expenses
are $2.5 million and include the utilities. This again is an estimate and
subject to change as the State and City work through the final design of the
project. Funding for the general fund portion of the project will be through
general obligation bonds. City staff has structured our debt since 2001 to
include this project. The major issue is that the project was anticipated to be
in the 2010 to 2015 timeline and the debt is pushing into other major projects
(Mulberry, Madison).
Staff has
been working with the Council on meeting with our legislators to encourage
additional funding to move the date of the project ahead. The March 5th
meeting will have a proposed resolution to cover some of these issues. The
earliest the project could be completed if additional State funds where
approved appears to be 2018.
Staff has
already begun to evaluate the street after this year’s extensive freeze/thaw
period to determine if we’ll recommend some maintenance improvement in 2014.
RECOMMENDATION
The street is well
past the expected life cycle for the construction type and needs extensive improvements.
I believe that the City must approve the agreement and start planning around
this project.
No comments:
Post a Comment