Tyranena substation
o Substation is now expected to be energized and in service by November 19,
o Contractor is completing final tests and coordination settings on breakers and switches,
o Discovered a trip mechanism breaker in the existing CP substation that had failed while performing the coordination of breakers – we’ve been nursing this breaker along for about a year, the breaker is now permanently bypassed and will not be needed when the new sub is in service,
o Installation of two feeder circuits to south must be completed before energizing, working with landowner to secure easements for a portion of these feeders,
o SCADA system will be completed after the station is energized, and ATC is doing final testing on the transmission line.