Tuesday, October 20, 2009

CP/Owen/Prairie Sanitary Sewer Project by Brian Beaulieu

As of the end of the day Friday the 16th, each crew is in the following position:

· Miles Narveson’s crew was 131 feet upstream of the intersection of Owen and CP. They have installed 1031 LF of mainline pipe with 1869 LF left to go. They also have 6 manholes left to install, as well as the laterals on Prairie south of Mulberry.

· Tom Birch’s crew has installed Manhole #18 near the TID #4 basin at the end of Cherokee Path. They have also installed all of the mainline pipe in the Alternative bid area north of Mulberry Street. They have yet to complete all of the laterals along Prairie north of Mulberry.

So far, the crews have been averaging between 45 and 50 hours per week, and have yet to work on Saturday. Including today, there are 20 week days and 4 Saturdays remaining until the contract completion date. At the current rate of pipe installation, Rawson should be able to get all of the pipe in the ground by the completion date, but they may not be able to get all of the trench areas prepped and paved.

No comments:

Post a Comment