Lake Mills Light and Water owns a water production facility called Well #4. Well #4 and the associated reservoir are located at the intersection of Franklin and Owen Streets. The reservoir is currently in average to poor condition and needs maintenance work.
The Council awarded a contract to L.C. United Painting Co. on May 17th, 2009 to complete the maintenance work recommended by Strand & Associates in their report dated October 2008. L.C. United Painting Co. is scheduled to start work on the reservoir June 24th and plans on completing the work with 14 work days.
The work includes weld repairs, welding containment logs, cleaning the tank interior, and rigging for sand blasting. They will then start blasting the interior to remove the old paint. They will finalize the work by blasting and painting the exterior of the tank.
Hopefully, all work will be completed by July 17th.