Prior
Council Action:
- In July of 2010, staff prepared a
memo for the Public Works Board to present new street projects for Capital
Improvement Plan that listed Campus as one of the top priorities.
- In November of 2011, the Public
Works Board determined that Campus Street would be a maintenance priority
in 2012.
- In November of 2011, City Council
approved a budget with the maintenance funds adequate to complete the
Campus Street Project.
- In May of 2012, staff prepared a
memo for the Public Works Board indicating that the Campus Street Plans
included storm sewer, street base, pavement, sidewalk and curb and gutter
improvements.
- On August 7, 2012, the
City Council reviewed the proposed bids for the project and voted to approve
awarding the contract 2-2012, Campus Street Project to B. R. Amon &
Sons, Inc of Cambridge, WI for $98,023.35.
- In
May of 2012, the City Manager authorized the engineer to prepare the construction
documents needed to bid the project. The engineer worked with staff on
design issues and city crew utilization.
- In
July, the City Manager sent the LMASD a set of preliminary plans for the
Campus Street Project and provided a potential timeline. The project was
advertised on July 19th and 26th. The DNR asked for
more storm water information on the 30th and the engineer
responded with the appropriate information.
- In
August, the bid opening was held on the 2nd. B. R. Amon &
Sons, Inc of Cambridge, WI bid of $98,023.35 was the lowest qualified bid.
There were six bidders. The DNR notified the engineer on August 6th
that the city would need to modify the storm water plans. The City Council
awarded the bid to B. R. Amon & Sons, Inc of Cambridge, WI for
$98,023.35.00 contingent on specific storm water improvements and
authorized the City Manager to sign the agreement. The DNR approved the
city’s proposal for a modified storm water plan consistent with the
Council’s direction.
- The
WPDES permit for Construction Site Storm Water Runoff was issued on August
14th. The contract documents were effective on August 23rd.
- On
September 4th, a pre-construction meeting was held. The
contractor started pavement removal on the 10th and then started
installed the storm sewer on the 19th. City crews removed the
sidewalk and curb and gutter starting on the 12th. Rennhack
started pouring the curb and gutter on the 20th. B. R. Amon
finished paving Campus Street and the parking area October 3rd.
- The
City worked with Bruce Johnson on upgrading the private storm sewer on his
property.
- The
first Pay Request was submitted to the City on November 11th
$93,079.35. This had a 2% retainage
remaining for punch list items and a net deduct of $3,044.42.